The time for action is upon us!
The RFP for Rutger Park is closing this coming Tuesday, and the RPRP Selection Committee will meet BRIEFLY (no more than 30 minutes) on Tuesday, September 6 at 7:30 pm at 3 Rutger Park to pick up copies of proposals for review and to go over our next steps. THIS MEANS YOU!
You will have from the evening of the 6th until that Friday, September 9 to review and independently score ALL received proposals based on our written criteria.
The full Selection Committee will meet, schedule depending, either over the weekend of the 10th and 11th or on Monday September 12 to collectively review and consensus score the proposals. We will announce the top four (4) scoring proposals on September 12, and will immediately schedule in-person, on-site interviews during the week of September 12 - 16. Final Selection Committee recommendation to the full Board, and official vote following in rapid succession.
The official schedule is summarized as follows:
Receipt of RFP/ RFQ Responses – September 6, 2011 by 5 pm
Candidates Selected for Interview -- September 12, 2011
Interviews Completed -- September 16, 2011
Consultant Selected -- September 19, 2011
Consultant Engagement -- September 23, 2011
Draft Documents -- HSRs, June 2012; CLRs, September 2012
Final Documents -- HSR, July 2012; CLRs, October 2012
Presentation of Documents -- November 2012
Possible Limited Construction -- Spring/Summer 2012
Happy Labor Day Weekend!
RPRP